Case Study Two

Replacement of a chiller from the Radisson Edwardian Hotel in Manchester

Get a Quote

Fill all information details to consult with us to get sevices from us

    Project Details

    • Replacement of a chiller from the Radisson Edwardian Hotel in Manchester
    • 8.6 Tonnes @ 28 Metre Radius, 20 Metre Lift Height. 74.77 Metre Boom. 8 Point lift with spreader beams in a one-over-two configuration.
    • Grove GMK 6300L
    • Removing this defective chiller was always going to be a challenge due to the weight, height of the building and surrounding environment. We liaised directly with Manchester City Council on behalf of our client in arranging the necessary permits and temporary traffic regulation orders. The crane was sited on a paved area and extra Ethafoam was supplied by ourselves to prevent the surface from being damaged. The crane was carefully selected as it was the only available machine capable of doing the job that could carry out the lifts using it’s main boom only.